As you can see from above image, some workers were busy with bundling the beams rebar under sound weather condition on April 14, 2015. The second phase of First Military Regulations Square which is covered with 20,000square meters is linked together with the Monument of First Military Regulations (the first phase). Red Star Square and commemorate & exhibition hall are the two main parts of it. The construction work for commemorate &exhibition hall which is covered about 8,000square meters was started in the beginning of this year. Currently, the frame construction for the first floor has been finished, and the plane construction work for the second floor was being proceeded to bundle the beams rebar on April 13, 2015. The whole project was estimated to be completed in the end of this June.