When reporters arrived at the site of 220kv power transmission station of Guidong County, technicians were busy in debugging a 220kv transformer. Other ancillary work (including transmission lines) has been completed. The substation has been established on the northwest of Datang Industrial park of Guidong County.
It was learned that this 220kv substation project was invested with 320 million yuan and launched at the beginning of 2012, including 220kv transmission line project with 54.302kms and 163 new towers and passing through 7 towns of Rucheng county and Guidong county.
The project principal introduced that the 220kv transformer would be fully installed at the end of this October, adjusted and placed to trail operation before November, and placed to operation in December.